Can the management team please invite Darrell to the blog?
e-mail: anddarrell@gmail.com
Ozonesonde logbook
Tuesday, March 1, 2011
DATA
all data files have been sent to everyone. Let me know if you didn't get them.
Not included: scanned checklist, audio files.
Thanks,
Patrick.
Not included: scanned checklist, audio files.
Thanks,
Patrick.
RC 367 launch schedule
8:35-go over schedule
8:45-pre-flight check, go over forecast
9:05-move equipment to launch trailer
9:25-set up laugh site
9:40-30 minute call
10:05-5 minute call
10:10-launch
Pre-flight checks:
Radiosonde S12109 frequency 402
Balloon track done with 600 gram balloon
Data in lab looks good
8:45-pre-flight check, go over forecast
9:05-move equipment to launch trailer
9:25-set up laugh site
9:40-30 minute call
10:05-5 minute call
10:10-launch
Pre-flight checks:
Radiosonde S12109 frequency 402
Balloon track done with 600 gram balloon
Data in lab looks good
Monday, February 28, 2011
Launch Forecast deux
Pretty much what Matt said.
Here are some maps for your viewing pleasure.
precipitation
http://www.nco.ncep.noaa.gov/pmb/nwprod/analysis/namer/namp03/00/images/nam_p03_084m.gif
250mb map
http://www.nco.ncep.noaa.gov/pmb/nwprod/analysis/namer/hiresw/00/images/hiresw_250_048m.gif
850mb map
http://www.nco.ncep.noaa.gov/pmb/nwprod/analysis/namer/hiresw/00/images/hiresw_850_048m.gif
Weather Underground Forecast.
http://www.wunderground.com/cgi-bin/findweather/getForecast?query=77205
Here are some maps for your viewing pleasure.
precipitation
http://www.nco.ncep.noaa.gov/pmb/nwprod/analysis/namer/namp03/00/images/nam_p03_084m.gif
250mb map
http://www.nco.ncep.noaa.gov/pmb/nwprod/analysis/namer/hiresw/00/images/hiresw_250_048m.gif
850mb map
http://www.nco.ncep.noaa.gov/pmb/nwprod/analysis/namer/hiresw/00/images/hiresw_850_048m.gif
Weather Underground Forecast.
http://www.wunderground.com/cgi-bin/findweather/getForecast?query=77205
Solutions changed...Ready for flight tomorrow
Solutions have been changed on the ozonesonde and tested. Looks like all is well for flight tomorrow. The pre-flight prep team will arrive at 8 am to make sure everything is still a go. Thanks, James.
Sunday, February 27, 2011
Launch Forecast
It looks like great weather for Tuesday mornings launch with cool/mostly clear conditions expected at the time of the launch. Winds should generally be light (0-5mph) out of the north-northeast as high pressure settles into the region. Rather strong upper level winds should allow the balloon to land well outside of Beltway 8...it currently looks like it will likely land somewhere east-southeast of Houston towards southwest Louisiana or the northwestern Gulf.
Thursday, February 24, 2011
Homework for Tuesday and schedule
Go to
http://imaqs.uh.edu/ozone/ourdata.htm
pick a sounding and plot in igor.
Day of Prep Team meet at 8:00 in lab
All other groups meet in lab at 8:30
we will walk over to trailer, set up, make calls, make sure telemetry is working
Launch around 9:15am
Watch data come in.
Flight will last around 2 hours.
http://imaqs.uh.edu/ozone/ourdata.htm
pick a sounding and plot in igor.
Day of Prep Team meet at 8:00 in lab
All other groups meet in lab at 8:30
we will walk over to trailer, set up, make calls, make sure telemetry is working
Launch around 9:15am
Watch data come in.
Flight will last around 2 hours.
Subscribe to: